Summary of the procedure
 

Where to go? (2)

You will have to go to the following agencies. The number indicates how many interactions are required with each entity.
Kenya Commercial Bank
4
Kenya Commercial Bank
Kisumu City Hall (x 4)
5 6 8 9
Kisumu City Hall

What you will get (3)

The objective of the procedure is to obtain those documents.
Authenticated Architectural plans
9
Authenticated Architectural plans
Authenticated structural plans
9
Authenticated structural plans
Construction permit
9
Construction permit

Required documents 

The documents with green band will be provided to you during the procedure.

Architectural drawing (x 2)
2 8
Architectural drawing
Survey plan
2
Survey plan
Proof of land ownership
2
Proof of land ownership
Structural drawings (x 2)
2 8
Structural drawings
Structura idemnity form
2
 Structura idemnity form
Architectural design report
2
Architectural design report
Structural design calculations
2
Structural design calculations
Engineer's practicing certificate
2
Engineer's practicing certificate
Architect's practising certificate
2
Architect's practising certificate
Change of use
2
Change of use
Construction permit invoice (x 2)
4 5
Construction permit invoice
Bank deposit slip
5
Bank deposit slip
Billed receipt
6
Billed receipt
Notification of approval
8
Notification of approval

How much?

Estimated cost of the procedure  KES  22,400

change the values with the

Cost detail

Estimate your cost

KES 3,400
Minimum charges for architectural fees for a commercial building measuring below 46metres -estimate
KES 3,000
Minimum charges for structural fees for a public facility measuring below 46metres-estimate
KES 2,000
For construction board fee
KES 1,000
For inspection of building files and sheet
KES 3,500
For occupation certificate for a commercial & industrial building measuring below 48metres - estimate
KES 7,000
For Public Health Inspection fee for commercial multistorey building-estimate
KES  1,000 per Beacon
- KES 0
For beacon identifiction or verification
0
KES 2,500
For Environmental Impact Assessment site verification fee
KES  5,000 per floor
- KES 0
For building inspection
0

How long ?

The estimated total time is calculated by adding the time spent: 1) waiting in queue, 2) at the counter and 3) between steps.
  Min. Max.
Total time (sum): 9 d 28 d
of which:
Waiting time in queue (sum): 15mn 50mn
Attention at counter: 45mn 3h. 50mn
Waiting time until next step (sum): 9 d 28 d

Legal justification?

The regulations which justify the procedure and its content
Architects and Quantity Surveyors Act Architects and Quantity Surveyors Act
  Sections 7, 8, 9
Building Code Building Code
  Sections 3, 4, 5, 7, 8, 9, 10, 11
Kisumu county Finance Bill 2014 Kisumu county Finance Bill 2015
Physical planning Act Physical planning Act
  Sections 4th schedule, 30, 31, 32
Survey act Survey Act
  Sections 30, 32, 33