List of steps
(Total number of steps: 5)
Obtain type approval of ICT equipment  (5)

Preview & Print

Properties
 
Summary of the procedure
 

Where to go? (1)

You will have to go to the following agencies. The number indicates how many interactions are required with each entity.
Communications Authority of Kenya (x 5)
1 2 3 4 5
 Communications Authority of Kenya

What you will get (1)

The objective of the procedure is to obtain those documents.
Final type approval
5
Final type approval

Required documents 

The documents with green band will be provided to you during the procedure.

Type approval application form
1
Type approval application form
Letter of agency
1
Technical manual
1
Technical manual
User manual
1
User manual
Conformance certificate
1
Test results
1
Compliance certificate
1
Communication Authority official receipt
3
Communication Authority official receipt

How much?

Free of charge

How long ?

The estimated total time is calculated by adding the time spent: 1) waiting in queue, 2) at the counter and 3) between steps.
  Min. Max.
Total time (sum): 110 d 160 d
of which:
Waiting time in queue (sum): 0mn 5mn
Attention at counter: 5mn 10mn
Waiting time until next step (sum): 110 d 160 d

Legal justification?

The regulations which justify the procedure and its content
Importation Type Approval And Distribution Of Communications Equipment Regulations 2010 Importation Type Approval And Distribution Of Communications Equipment Regulations 2010
  articles 4, 10, Regulation 3, Regulation 7, Regulation 8
The Kenya Communications Regulations, 2001 The Kenya Communications Regulations, 2001
  articles Regulation 52 and 57, Regulations 57