steps (8) arrow_drop_up arrow_drop_down
Obtain electricity generation, distribution and supply licence  (8) expand_more expand_less

print Summary

Preview & Print

Properties

7
Inspection
(last modified: 16/01/2018)

Timeframe ( ver detalles )

Espera hasta paso siguiente

0 mn  -  0 mn
10 days  -  53 days

Contact details

Entity in charge

Energy Regulatory Commission

Eagle Africa Centre, Longonot road, Upperhill. P. O. Box 42681 , Nairobi 00100
Tel: +254 202 847 000/+254 202 847 200
Tel. 1: +254 202 717 603
Website: www.erc.go.ke

Unit in charge

Electricity department

Mon: 08:00-13:00, 14:00-17:00
Tue: 08:00-13:00, 14:00-17:00
Wed: 08:00-13:00, 14:00-17:00
Thu: 08:00-13:00, 14:00-17:00
Fri: 08:00-13:00, 14:00-17:00

Requirements

1. Inspection checklist
Inspection checklist (copy)
2. 01 - Libre deuda de patente
Physical presence
Of the applicant or the representative

Time frame

Attention at counter: Min.  20mn - Max.  1h
Waiting time until next step: Min.  10 days - Max.  53 days

Legal justification

1. Energy Act
Energy Act
Section 63

Recourse: Energy Regulatory Commission

Entity in charge

Energy Regulatory Commission

Eagle Africa Centre, Longonot road, Upperhill. P. O. Box 42681 , Nairobi 00100
Tel: +254 202 847 000/+254 202 847 200
Tel. 1: +254 202 717 603
Website: www.erc.go.ke

Unit in charge

Electricity department

Mon: 08:00-13:00, 14:00-17:00
Tue: 08:00-13:00, 14:00-17:00
Wed: 08:00-13:00, 14:00-17:00
Thu: 08:00-13:00, 14:00-17:00
Fri: 08:00-13:00, 14:00-17:00

Person in charge

Eng. Joseph Oketch

Director-Electricity department
Powered by eRegulations ©, a content management system developed by UNCTAD's Business Facilitation Program and licensed under Creative Commons License