Obtain petrol service station construction permit  (5) expand_more expand_less

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions/Systems involved 2 expand_more expand_less

EPRA Portal (x 2)
Energy & Petroleum Regulatory Authority (x 3)

Results 1 expand_more expand_less

Petrol service station construction permit

Required Documents expand_more expand_less

Certificate of incorporation
Identity card (x 2)
Proof of land ownership
Notification of approval of development permission
Environmental Impact Assessment license
Approval of construction of an acceleration and deceleration lane
Mechanical engineer's drawings
Civil engineer’s drawings

Cost Free

expand_more expand_less

Free of charge

Total Duration 4d 1/2 - 46d  expand_more expand_less

  Min. Max.
Total time (sum): 4d 1/2 46d
of which:
Waiting time in queue (sum): 10mn 20mn
Attention at counter: 1h. 20mn 2h. 45mn
Waiting time until next step (sum): 4d 45d

Laws 2 expand_more expand_less

Energy Act Energy Act
  Sections 10, 11
Petroleum Act 2019 Petroleum Act 2019
  Sections 86, 87