Steps (6) arrow_drop_up arrow_drop_down
Obtain petroleum jetty construction permit  (6) expand_more expand_less

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions/Systems involved 2 expand_more expand_less

EPRA Portal (x 3)
Energy & Petroleum Regulatory Authority (x 3)

Results 0 expand_more expand_less

-

Required Documents expand_more expand_less

Certificate of incorporation
List of shareholders and directors- CR 12
Physical planning approval
Mechanical engineer's drawings
Civil engineer's drawings
Environmental Impact Assessment report
Environmental Impact Assessment license
Class G work permit
Identity card (x 2)

Cost Free

expand_more expand_less

Free of charge

Total Duration 3d 1/2 - 19d  expand_more expand_less

  Min. Max.
Total time (sum): 3d 1/2 19d
of which:
Attention at counter: 35mn 1h. 55mn
Waiting time until next step (sum): 3d 18d

Laws 2 expand_more expand_less

Energy Act Energy Act
  Sections 10, 11
Petroleum Act 2019 Petroleum Act 2019
  Sections 86, 87