Register project with NCA  (4) expand_more expand_less

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions/Systems involved 2 expand_more expand_less

National Construction Authority portal (x 3)
National Construction Authority (NCA)

Results 1 expand_more expand_less

Compliance certificate

Required Documents expand_more expand_less

Authenticated architectural plans (x 2)
Authenticated structural plans (x 2)
Nema approval (x 2)
Bill of quantities (x 2)
Contract / Agreement (x 2)
Contractor's registration certificate (x 2)
PIN certificate (x 2)
Authenticated notification of approval (PPA2) (x 2)
Supervision letters (x 2)

Cost Free

expand_more expand_less

Free of charge

Total Duration 3d  - 10d  expand_more expand_less

  Min. Max.
Total time (sum): 3d 10d
of which:
Attention at counter: 1h. 15mn 2h. 30mn
Waiting time until next step (sum): 2d 1/2 9d

Laws 2 expand_more expand_less

National construction authority act National Construction Authority Act
  Sections 5, 6, 31
National Construction Authority Regulations National Construction Authority Regulations
  Sections 17, 18