Obtain electricity distribution licence  (6) expand_more expand_less

arrow_drop_up arrow_drop_down
chevron_right print

Preview & Print

Properties

Summary of the procedure

Institutions involved 1 expand_more expand_less

Energy Regulatory Commission (x 3)
Energy Regulatory Commission

Results 1 expand_more expand_less

Electricity distribution licence

Required Documents expand_more expand_less

Newspaper advertisement
Notice to local authority
Description of the undertaking
Route sketch
Route sketch
Environmental Impact Assessment license
Environmental Impact Assessment license
List of shareholders and directors- CR 12
List of shareholders and directors- CR 12
Approved power purchasing agreement
Engineer's report
Engineer's report
KES 10,000
For licence application
  Min. Max.
Total time (sum): 1 d 91 d
of which:
Attention at counter: 5mn 10mn
Waiting time until next step (sum): 0 d 90 d
Energy (Electricity Licensing) Regulations, 2012
Energy Act Energy Act