print

Preview & Print

Properties

Preview & Print

Properties

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions involved 3 expand_more expand_less

Ministry of Energy and Petroleum, (x 2)
Ministry of Energy and  Petroleum,
Energy & Petroleum Regulatory Authority (x 9)
Kenya Commercial Bank

Results 2 expand_more expand_less

Approved power purchase agreement
Electricity generation licence

Required Documents expand_more expand_less

Environmental Impact Assessment license (x 2)
Engineer's report (x 2)
Route sketch (x 2)
Certificate of compliance with the physical planning act (x 2)
Newspaper advertisement (x 2)
Approved power purchasing agreement (x 4)
Audited accounts (x 2)
Printed application
Bank deposit slip
Application forwarding letter
Electricity generation inspection checklist
Identity card

Estimated cost KES  10,000

expand_more expand_less

USD expand_more expand_less
  • USD Add Name Here
KES 10,000
For licence application

Total Duration 12 d - 91 d expand_more expand_less

  Min. Max.
Total time (sum): 12 d 91 d
of which:
Waiting time in queue (sum): 10mn 40mn
Attention at counter: 1h. 40mn 8h. 50mn
Waiting time until next step (sum): 12 d 90 d

Laws 2 expand_more expand_less

Energy (Electricity Licensing) Regulations, 2012
Energy Act Energy Act
Powered by eRegulations ©, a content management system developed by UNCTAD's Business Facilitation Program and licensed under Creative Commons License