print

Preview & Print

Properties

Preview & Print

Properties

Steps (13) arrow_drop_up arrow_drop_down
Obtain approval of power purchasing agreement  (5) expand_more expand_less
Obtain electricity generation licence  (8) expand_more expand_less

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions involved 3 expand_more expand_less

Energy Regulatory Commission (x 6)
Kenya Power and Lighting Company
Kenya Power and Lighting Company
Kenya Commercial Bank

Results 1 expand_more expand_less

Electricity generation licence

Required Documents expand_more expand_less

Feasibility study
Expression of interest
Environmental Impact Assessment license (x 3)
Change of user
Construction permit
Power purchasing agreement
Kenya civil aviation clearance
Special use licence
Wayleave consent
Engineer's report (x 2)
Route sketch (x 2)
Certificate of compliance with the physical planning act (x 2)
Newspaper advertisement (x 2)
Approved power purchasing agreement (x 4)
Audited accounts (x 2)
Printed application
Bank deposit slip
Application forwarding letter
Electricity generation inspection checklist
Identity card

Cost KES  10,000 expand_more expand_less

KES 10,000
For licence application

Total Duration 12 d - 91 d expand_more expand_less

  Min. Max.
Total time (sum): 12 d 91 d
of which:
Waiting time in queue (sum): 10mn 40mn
Attention at counter: 1h. 45mn 9h.
Waiting time until next step (sum): 12 d 90 d

Laws 2 expand_more expand_less

Energy (Electricity Licensing) Regulations, 2012
Energy Act Energy Act
Powered by eRegulations ©, a content management system developed by UNCTAD's Business Facilitation Program and licensed under Creative Commons License