Steps (8) arrow_drop_up arrow_drop_down
Obtain electricity generation, distribution and supply licence  (8) expand_more expand_less

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions involved 2 expand_more expand_less

Kenya Commercial Bank
Energy Regulatory Commission (x 4)

Results 1 expand_more expand_less

Electricity generation, distribution and supply licence

Required Documents expand_more expand_less

Environmental Impact Assessment license (x 2)
Engineer's report (x 2)
Route sketch (x 2)
Certificate of compliance with the physical planning act (x 2)
Newspaper advertisement (x 2)
Audited accounts (x 2)
End user tariff (x 2)
Electricity supply contract (x 2)
Customer service charter (x 2)
Complaint handling procedure (x 2)
Printed application
Application forwarding letter
Bank deposit slip
Inspection checklist

Cost KES  10,000 expand_more expand_less

KES 10,000
For licence application

Total Duration 12 d - 91 d expand_more expand_less

  Min. Max.
Total time (sum): 12 d 91 d
of which:
Waiting time in queue (sum): 5mn 30mn
Attention at counter: 45mn 2h. 10mn
Waiting time until next step (sum): 12 d 90 d

Laws 4 expand_more expand_less

Energy (Licensing) Regulations, 2012 Energy (Licensing) Regulations, 2012
  articles 5, 16, 17, Reg 15, Reg 4, Reg 6
Energy Act Energy Act
  Sections 27, 28, 30, 31, 63
Kenya National Distribution Grid Code Kenya National Distribution Grid Code
Kenya National Transmission Grid Code Kenya National Transmission Grid Code