Steps (20) arrow_drop_up arrow_drop_down
Obtain site approval  (4) expand_more expand_less
Architectural plans approval  (6) expand_more expand_less
Obtain Public health approval  (2) expand_more expand_less
Obtain Environmental Impact Assessment license  (4) expand_more expand_less
Obtain hatchery licence  (4) expand_more expand_less

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions involved 7 expand_more expand_less

Nairobi city county government -Subcounty veterinary office
Nairobi City County Veterinary Services (x 5)
City Hall Annexe (x 4)
Cash office - City Hall
City Hall (x 2)
Environmental Impact Assessment Expert (x 2)
National Environmental Management Authority Nairobi County Office (x 2)

Results 5 expand_more expand_less

Physical planning approval
Authenticated architectural plans
Construction permit
Environmental Impact Assessment license
Hatchery licence

Required Documents expand_more expand_less

Hatchery application letter
Proposed waste disposal mechanism for the hatchery
Disclaimer form
Disclaimer form
Architectural drawing (x 4)
Survey plan
Land rates clearance receipt
Proof of land ownership (x 3)
Change of user
Construction permit invoice
Notification of approval of architectural plans
Certificate of incorporation
Company PIN Certificate
EIA submission form
Project report
Identity card
EIA expert practising license
Evidence of Public participation
Authenticated architectural plans
Environmental Impact Assessment license

Cost KES  297,200 expand_more expand_less

KES 30,000
For site construction board
KES 211,200
For construction fee for a four storeys office block measuring 200Metres squared per floor - estimate
KES 50,000
For preparation of the project report -estimate
KES 1,000
For hatchery application fees
KES 5,000
For hatchery licence

Total Duration 57 d - 91 d expand_more expand_less

  Min. Max.
Total time (sum): 57 d 91 d
of which:
Waiting time in queue (sum): 20mn 45mn
Attention at counter: 3h. 5mn 17h. 50mn
Waiting time until next step (sum): 57 d 90 d

Laws 10 expand_more expand_less

Animal diseases(Hatcheries) rules Animal diseases(Hatcheries) rules
  Sections 3, 4, 6-12 ,  Article 1st schedule
Architects and Quantity Surveyors Act Architects and Quantity Surveyors Act
  Sections 7, 8, 9
Bio security in poultry production Bio security in poultry production
Building Code Building Code
  Sections 3, 4, 5, 6, 7, 8, 9, 10, 11 ,  articles 3, 4, 5, 6, 7, 8, 9, 10, 11
Environmental Impact Assessment and Audit regulations 2003 Environmental Impact Assessment and Audit regulations 2003
  Sections 1st schedule, 7, 8, 9, 10
Environmental Management and Co-rdination (Amendment)ACT 2015 Environmental Management and Coordination (Amendment)ACT 2015
  Section  43
Environmental Management and coordination ACT Environmental Management and coordination ACT
  Sections 2, 58, 59, 60, 61, 62, 63, 64
Construction permit fees chart Guideline of fees and charges
Physical planning Act Physical planning Act
  Sections 4th schedule, 30, 31, 32, 33, 34, 35, 37, 38, 39, 40, 41, 42, 43, 44
Survey act Survey Act
  Sections 30, 32, 33