Steps (4) arrow_drop_up arrow_drop_down
Register project with NCA  (4) expand_more expand_less

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions/Systems involved 2 expand_more expand_less

National Construction Authority portal (x 3)
NCA Eldoret office

Results 1 expand_more expand_less

Compliance certificate

Required Documents expand_more expand_less

Authenticated architectural plans (x 2)
Authenticated structural plans (x 2)
Bill of quantities (x 2)
Contract / Agreement (x 2)
Contractor's registration certificate (x 2)
PIN certificate (x 2)
Uasin Gishu county development permission (PPA2) (x 2)
Nema approval (x 2)
Practising licence (x 2)
Fuel retail site construction permit (x 2)
KERRA approval (x 2)

Cost Free

expand_more expand_less

Free of charge

Total Duration 3d  - 10d  expand_more expand_less

  Min. Max.
Total time (sum): 3d 10d
of which:
Attention at counter: 1h. 15mn 2h. 30mn
Waiting time until next step (sum): 2d 1/2 9d

Laws 2 expand_more expand_less

National construction authority act National Construction Authority Act
  Sections 5, 6, 31
National Construction Authority Regulations National Construction Authority Regulations
  Sections 17, 18